Client: Tier 1 Contractor | Sector: Wastewater | Value: £23,800,000.00
Belasco Associates were engaged by a Tier 1 Contractor involved in the design and construction of a replacement Sewage Treatment Works (STW) in Jersey to manage the account of one of their major civil and M&E Subcontractors. The Subcontractor was appointed under an ECC NEC Option A contract (lump sum with activity schedule) and our services included the following:
- Managing Subcontractor Early Warnings
- Managing the Subcontract Risk Register
- Assessment, valuation and submission of Compensation Events, up and down the contractual chain
- Advising the Client on matters relating to extension of time, delay and mitigation
- Assessment of Subcontractor extensions of time
- Assessment of Subcontractor loss and expense
- Advising on potential adjudication strategy and
- Advising the Client on potential termination of the Subcontractor for breach of contract